Mill & Overlay Project: 125th & East French Lake Road 

The City is making improvements to 125th and East French Lake Road.  The project involves resurfacing the existing roadway without any changes to its current alignment or width.  The road will remain open to traffic throughout the duration of the work; however, please expect delays within the construction zone. 

Currently, we are still waiting on an updated detail schedule, but verbally we have been told the information below.  This is a tentative schedule and is weather dependent.

The anticipated timeline is as follows:


Concrete Curb & Gutter:                               October 15th, 2025
Milling the Bituminous                                October 20th, 2025
Bituminous Paving:                                       October 27th, 2025

If you have any questions, please contact Nick Findley at (952) 334-0653 or Martin Farrell at (612) 751-8847